Rice University’s Student Newspaper — Since 1916

Saturday, August 31, 2024 — Houston, TX

NESB construction remains on schedule amid other delays

nesb-construction-zeisha-bennett-web
Zeisha Bennett / Thresher

By Lindsey Ran     4/5/22 11:05pm

The New Engineering and Science Building construction remains on schedule despite the recent disruption of multiple construction projects at Rice caused by pandemic-induced supply chain and inflation issues.

According to Associate Vice President for Facilities Engineering and Planning Kathy Jones, the initial interior buildout of the new building is targeted for completion by the summer of 2023.

“The Abercrombie Building, which is also currently known as the New Engineering and Science Building, is being constructed in phases,” Jones wrote in an email to the Thresher. “Subsequent construction will occur to complete the interior buildout of additional research labs. The NESB does not have any mass structural timber as part of the building design, therefore the schedule has not been impacted due to timber shortages.”



However, Jones said that COVID has impacted other aspects in the construction of the NESB, especially through the inflated cost of materials. 

“The team anticipated COVID-related cost increases from the beginning of the project,” Jones wrote. “Most of the increases have been related to construction material escalation, which was driven by supply chain issues. Overall, we have been able to counter that by separating the project into multiple design packages in order to buy material like steel and concrete and mechanical and electrical equipment early before further cost escalation.”

Provost Reginald DesRoches said that the demolition of the old Abercrombie Building and construction of the NESB were necessary due to the outdated nature of the Abercrombie Building.

“Abercrombie Laboratory had reached the end of its useful life,” DesRoches wrote in an email to the Thresher. “Many features of the building were not up to the current code and the labs in the building could not support state-of-the-art research. Past renovations of the building to meet contemporary research needs were expensive because the building did not have the necessary infrastructure to support today’s research programs and endeavors.”

Jones said that the engineering departments that were previously housed in the Abercrombie Building have been transported to temporary locations across campus.

“Former occupants of the Abercrombie Laboratories Building have been relocated to various other buildings on campus according to their programmatic needs and where space was available,” Jones wrote. “All of these moves, with the exception of a few, are considered temporary.”

The NESB building has essentially finished its vertical construction, according to Department Chair of Chemical and Biomolecular Engineering Michael Wong.

“They’re going to do a top-off event this week or next week, where they define the top-off as the highest the building will go,” Wong said. “If you define finishing as how high it goes, it will be finished already now. Of course, it’s not ready to move in yet … [but] the building will have its first occupants one year from now.”

Move-in has been divided into multiple waves. The Department of Chemical and Biomolecular Engineering will be among the first to re-enter the building, according to Wong.

“The first stage is several research laboratories, myself included, and maybe two or three other ones from engineering and from natural sciences,” Wong said. “I’m guessing that by the middle of spring we will be able to move some of our equipment in, and to have everyone fully move in maybe at the beginning of summer.”

Tony Yu, a Wiess College junior majoring in electrical engineering, said that he is looking forward to the new building.

“The old building isn’t aesthetically pleasing compared to the rest of campus,” Yu said. “I also think we can have more lab space since most of our labs were in Brockman.”

Wong said that he is excited for the new building to help revive the sense of community within his own department.

“I’m in the [Space Science and Technology Building], and my faculty and staff are literally in seven other buildings,” Wong said. “It’s kind of hard to have a good vibe when we’re all separate on campus. Even though the campus is cozy, it’s still nice to be in the same building instead of setting up a zoom meeting over email.”



More from The Rice Thresher

NEWS 8/30/24 2:50am
Rice gathers for vigil honoring Andrea Rodriguez Avila

Rice students and staff paid their respects to Andrea Rodriguez Avila in a candlelight service, held Aug. 28 in the Rice Memorial Chapel. Over a hundred attendees, including Andrea’s family, filled the chapel’s pews while dozens more stood to the side. The ceremony, hosted by community faith members, opened with remarks from Provost Amy Dittmar.

NEWS 8/27/24 11:50pm
Remembering Andrea Rodriguez Avila

On a spring night, Andrea Rodriguez Avila was wrapping up her Peer Academic Advisor training. Her close friend, Karen Martinez, wanted boba tea; it was nearing the end of the semester, and everything was "messy and unorganized," she said. The two went to The Tea Nook on campus — Andrea had never been. "We talked the whole way there," Martinez said, and all through their wait in the line.

NEWS 8/27/24 11:05pm
Rice adds ED II to application process

Rice introduced an Early Decision II plan June 17 that took effect in the 2024-25 admission cycle. Students applying in the ED II round must submit materials by Jan. 4, 2025 and will receive decisions by mid-February. The deadline for ED I remains unchanged from Nov. 1. 


Comments

Please note All comments are eligible for publication by The Rice Thresher.